By providing your contact information to Ragan Mckinney, your personal information will be processed in accordance with Ragan Mckinney's Privacy Policy. By checking the box(es) below, you expressly consent to receive marketing or promotional real estate communication from Ragan Mckinney in the manner selected by you. For SMS text messages, message frequency varies. Message and data rates may apply. Consent is not a condition of purchase of any goods or services. You may opt out of receiving further communications from Ragan Mckinney at any time. To opt out of receiving SMS text messages, reply STOP to unsubscribe. SMS text messaging is subject to our Terms of Use.
Thank you for your message. I will be in touch with you shortly.
Explore Our Properties
Sunlit neutral living room overlooking a curved driveway, late-fall lawn and mature trees at a semi-rural Ohio home.

Williamsburg and SR 32, East of the Finished Widening

November 26, 2026

Leave Williamsburg heading west on State Route 32 and the first stretch of the drive runs past the McKeever Road and Dela Palma Road crossings, which Williamsburg Township has asked to have rebuilt with a bridge and interchange. Since September, though, the trip ends differently. Past Olive Branch-Stonelick Road the signals are gone, and the road carries you up onto ramps and over the old Eastgate intersections to I-275 without a single stop.

The Clermont Sun reported that the last ramp, at Glen Este-Withamsville Road, opened in late September 2026. That ramp closed out a 13-year, $200 million program covering 4.5 miles between Bells Lane in Union Township and Olive Branch-Stonelick Road in Batavia Township. The County's own figure is that a drive which "used to take at least 25 minutes" on that stretch "now takes less than 10 minutes."

For a buyer weighing Williamsburg against Batavia or Amelia, the faster western stretch is now a given. It helps every address east of Bells Lane about equally. What actually separates one Williamsburg-area home from another is the eastern stretch the widening never reached. There, ODOT, the County's transportation district and Williamsburg Township are still working out which crossings stay open, which get rebuilt and when.

The Finished Road Stops at Olive Branch-Stonelick

The widening replaced or rebuilt six signalized connections: Eastgate Boulevard, Glen Este-Withamsville Road, Elick Lane, Old SR 74, Bach Buxton Road and Olive Branch-Stonelick Road. All six now use overpasses with raised ramps. Kris McClintick, the County's economic development director, told the Clermont Sun that "Purina's new manufacturing facility, residential development and investments by other companies east of Batavia toward Williamsburg are proof" of what the project set in motion.

You can see that residential development from the highway. In March 2026 the County named Harvest Meadows and Streamside along SR 32 in Batavia Township as large subdivisions under construction. Fischer Homes advertises Harvest Meadows as about 10 minutes from I-275. As of this fall its townhomes start at $276,900 and its Maple Street collection at $307,900. Those communities sit on the finished side of the project. Williamsburg sits farther east, and every trip from there to I-275 starts on the older road. We covered how that new-construction pipeline affects resale sellers in What Batavia's 1,800-Home Pipeline Means If You're Selling A Resale Home.

Half Acre Road Already Carries the Plant Traffic

Half Acre Road is where the eastern stretch changed first. Clermont County places the Nestlé Purina plant along Half Acre Road at SR 32, next to the South Afton Industrial Park and its new 2,000-foot access road. WCPO reported the plant's opening on August 31, 2026. The paper described a $550 million, 1.3-million-square-foot operation with more than 430 associates and plans to exceed 500.

The township started planning for that traffic well before opening day. According to the trustees' February 24, 2025 minutes, the plant's factory manager asked for help with traffic control. The township then arranged a meeting with two Clermont County representatives and six from ODOT to work on getting people out of the plant "timely and safely."

Two projects on Half Acre Road came out of that work. The Clermont County Transportation Improvement District is designing a roundabout at Half Acre Road and Afton Drive. ODOT's project file, PID 118757, shows $250,000 for detailed design. The trustees' October 13, 2026 minutes put the roundabout in Phase 1 engineering. The second project is the Half Acre Road bridge over SR 32. Under ODOT PID 116569, ODOT plans to replace the deck, raise the bridge and repaint it, with a current working estimate of about $6.16 million and 2030 listed as the project's target year. On August 24, 2026 the trustees approved $22,444 in engineering for "Williamsburg" lettering and blue steel on the rebuilt bridge. The plan is for the bridge to say Williamsburg when it's finished.

For a home search, Half Acre Road should get easier over the next few years, with a roundabout in design and a rebuilt bridge on ODOT's list. Expect work zones at that interchange during construction.

McKeever and Dela Palma Are the Crossings to Watch

McKeever Road and Dela Palma Road are the two crossings of SR 32 that Williamsburg Township has made its priority, and both are still unresolved. The township's Fall/Winter 2026 newsletter reports that ODOT has suggested eventually closing both crossings and routing that traffic to Eastwood Road. As of the newsletter, that idea is a suggestion and not an adopted plan.

The trustees answered on August 10, 2026, when they unanimously adopted Resolution 2026-20. It asks for a bridge and interchange "in the vicinity of McKeever Road and Dela Palma Road" and says it should be "implemented immediately." The resolution notes that the Eastwood Road site is in Brown County and that rerouted traffic could face a trip "up to over 3.5 miles away." It points to the existing Bruce Lunsford Way interchange in Brown County, 1.5 miles from Eastwood Road. The township's growth argument rests on named employers: Nestlé Purina and MillerKnoll's Design Within Reach operation, which are already in the township, and Swiss pharmaceutical manufacturer Lonza, which the resolution says "has expressed an interest" in locating there.

The trustees haven't ruled out a new bridge at Eastwood Road. After the vote, Trustee Chair Gary Jordan said the board is "not necessarily opposed to opening a bridge at Eastwood but not at the expense of closing off Dela Palma and McKeever Roads at SR 32." The township has informed the Village of Williamsburg, Jackson Township, the Village of Bethel and Tate Township of ODOT's suggestion. It is also looking for a consultant to run a full traffic study of the corridor. The County transportation district has offered to partner on an updated SR 32 East Corridor study covering Bauer Road to the Clermont-Brown County line.

For a buyer, the question is concrete. A home off Dela Palma Road or McKeever Road reaches SR 32 one way today. That route could change, or it could get a new interchange, depending on decisions that will be made over the next several years. A home in the village, closer to Old SR 32 and SR 133, depends on those two crossings less. That is a property-by-property question, and it belongs in the showing notes next to the roof age and the furnace.

The Township Is Also Drafting Its Next 20 Years

The traffic study runs alongside a second process. Williamsburg Township is updating its 20-year Land Use Plan with Clermont County's Community and Economic Development office. The township describes the priorities as "preserving our rural character, protecting natural resources, and encouraging responsible economic development along the State Route 32 corridor." The first public workshop met on November 17. The second is Monday, February 8, 2027 at 6:00 p.m. at the Williamsburg Township Emergency Services Building, 915 West Main Street, and the township expects to adopt the plan by June 2027.

The township's draft Story Map gives buyers an early look at where growth is headed. It describes the township as "trending away from pure agriculture toward industry and some housing, especially along State Route 32." It also notes that homes on sewer are concentrated in or next to the villages of Williamsburg and Batavia, that large-lot homes line corridors such as SR 133, and that higher-density townhomes and single-family homes are being built toward the township's western boundary. It names the South Afton Industrial Park, the Purina site and the Eastern Cincinnati Innovation Park east of Williamsburg as the industrial anchors. The same newsletter says the township Zoning Board is in the final steps of adding zoning language for data centers. If you're looking at acreage, our earlier post on what happens when Williamsburg farmland becomes a homesite pairs well with this map.

Why This Season Leaves Room for the Question

Buyers have a little more time to ask about road access right now than they had a year ago. According to the REALTOR Alliance of Greater Cincinnati, active inventory across Butler, Clermont, Clinton, Hamilton and Warren counties stood at 3,996 homes in October 2026. That's up 12.6% from October 2025. Median days on market rose 40% over the same period, to 14 days, while the median sold price of $309,000 rose just 0.6% year over year. Those are five-county figures, not Williamsburg figures. Still, more listings and slower sales across the region mean a buyer can usually take a day to drive a property's route to SR 32 at the hours they would commute, both west toward I-275 and east toward the plant traffic at Half Acre Road.

Our Williamsburg neighborhood page covers the village itself. For the township's growing industrial side, our post on the Purina plant's location explains why the plant is in Williamsburg Township even though most headlines call it the Batavia plant.

A Few Quick Answers

Is ODOT closing the McKeever Road and Dela Palma Road crossings? As of the township's Fall/Winter 2026 newsletter, closing them is something ODOT has suggested, not an adopted project. In Resolution 2026-20, adopted August 10, 2026, the township formally asked for a bridge and interchange near those crossings instead.

When will the Half Acre Road bridge over SR 32 be rebuilt? ODOT's project file for PID 116569 lists 2030 as the target year for the deck replacement and raising.

Where can residents weigh in? The township's Land Use Plan survey and Story Map are linked from williamsburgtownship.org, and the next public workshop is February 8, 2027. Trustee meetings are held on the second and fourth Mondays at 7:00 p.m. at the Emergency Services Building.

If you're comparing homes around Williamsburg and want to know which SR 32 crossing each one depends on, and what's planned for it, Ragan McKinney Real Estate is glad to talk it through with you before you write an offer. If you already own in the township and want to know how these corridor plans could affect your sale, start with a home valuation. Let's Connect.